Mainland Group Côte d’Ivoire Plant 3
Two complete 5 t/h TSR lines; both operate at a 330-second trolley interval and actual capacity reaches 5.24 t/h per line.
These seven documented rubber processing machinery projects cover complete TSR 10/20 natural rubber production lines in Côte d’Ivoire and Cambodia, automatic natural rubber bale packaging and robotic handling, an Indonesian palletizing system, and EPDM baling presses for Jilin Petrochemical in China. Each case links the project scope, operating result, equipment, and on-site media.

Two complete 5 t/h TSR lines; both operate at a 330-second trolley interval and actual capacity reaches 5.24 t/h per line.

One complete 5 t/h TSR line; the trolley interval is 300 seconds and actual capacity reaches 5.76 t/h.

One complete 5 t/h TSR line; the trolley interval is 280 seconds and actual capacity reaches 6.2 t/h.

Two complete 5 t/h TSR lines; the trolley interval is 320 seconds and actual capacity reaches 5.36 t/h per line.

Robotic bale unloading, automatic feeding, and automatic baling and packaging.

Robotic automatic palletizing and box loading.

Four SPR-A1 synthetic-rubber baling presses, with a design rate of 175 bales per hour and stable annual output of 40,000 tonnes.